Increase production with our standard ESP motor designed for conventional, unconventional, and shallow well conditions.
Challenge: Minimize the intervention frequency and choked production related to ESP erosion failures in wells with high solids production
Solution:
Results:
Production fluids with abrasive sand are a continuous challenge for artificial lift equipment because these fluids generate wear, reduce lifting efficiency, and increase the frequency of well interventions due to failures. High flow rates compound the problem by exacerbating the solids abrasion.
An operator in Colombia faced this scenario in the Llanos Field, where solids-laden fluid production compromised ESPs and threatened field economics—not only from frequent interventions to replace ESPs but also from restricting production to avoid even worse damage.
One well, for example, typically produced 10 to 100 ppm of solids but peaked with 1,000 ppm of solids in 13,000 to 15,000 bbl/d [2,067 to 2,385 m3/d] of fluid. Two ESPs in the well failed with an average run life of only 72 days, although the well production had been choked back to approximately 75% of its potential (11,800 bbl/d [1,876 m3/d]) in an attempt to reduce the scouring. The operator asked for a more robust solution.
SLB engineers began with thorough root cause analysis of the failed ESPs, finding significant erosion of impeller and diffusers, erosion and abrasion of the radial bearing, and damage to the pump head radial support.
The next step was to design a new Maximus install-ready ESP motor that could survive in the extremely abrasive downhole conditions. In particular, the engineering team selected
Engineers also developed a plan to restart the well production slowly to minimize solids churn and then ramp up production slowly.
The new ESP was installed in the well in June 2012 with a production target of 14,000 bbl/d [2,226 m3/d], which was 6,000 bbl/d [954 m3/d] less than the production from the prior ESPs. In the first 3 months, solids production reached as high as 130 ppm. After 6 months, the solids production dropped, and the production target was increased. The slow improvement continued, and the well eventually reached 21,000 bbl/d [3,339 m3/d], exceeding prior peak flow rates from the well.
The ESP continued to produce the solids-laden well fluids for 797 days—11 times longer than the average run life of the prior two pumps—before being pulled out of the well because the electrical cable and motor fatigued after reaching their normal run life. The pump housing, impellers, and diffusers were found to be in good condition with no significant wear, demonstrating the success of the engineering design.