Shuttle System Saves USD 95,000 and 5 Days of Deferred Production to Replace ESP | SLB

Shuttle system saves USD 95,000 and 5 days of deferred production to replace ESP

minus
Ecuador, South America, Onshore

Challenge: Minimize workover cost, deferred production, and HSE risks when replacing an ESP

Solution: Use coiled tubing instead of conventional jointed tubing and a workover rig to run the new REDA ESP™ pump into the installed Shuttle™ rigless ESP replacement system

Results:

  • Completed the replacement in 47 hours compared with at least 7 days for a conventional replacement, saving approximately USD 95,000 in workover costs and eliminating more than 5 days of deferred production
  • Minimized risk profile because the operation required only 12 people instead of the 40 required for a conventional workover rig

ESP runs 520 days before needing replacement

In 2015, an operator in Ecuador needed to replace an ESP in one of its wells. At the time, it was common for rigs and hoists to take 7 to 10 days to respond to an ESP failure and an additional 4 days to pull and replace the ESP on jointed tubing. To reduce the time and cost of subsequent replacements, SLB installed the new ESP as part of a Shuttle system.

After running for 520 days, the ESP failed and required replacement, providing an opportunity to demonstrate the value of the Shuttle system installed earlier.

ESP docking station technology speeds up replacements

The Shuttle system consists of a downhole docking station and retrievable ESP string. The docking station is attached to the end of the tubing. Inside the docking station are three connectors and landing shoulders that support the weight of the ESP and its reactive forces and prevent the motor from counter-rotating on startup.

The retrievable ESP string is made up of a motor connector, standard ESP assembly, and a bypass valve. The motor connector contains female wet connectors and has corresponding parts to orient and connect the ESP to the docking station, intake and discharge, as well as a bypass valve to allow fluid to drain on system retrieval.

Photo: The ZEiTECS Shuttle system enabled rapid ESP replacement without a workover rig, reducing costs and eliminating more than 5 days of deferred production.
The Shuttle system enabled rapid ESP replacement without a workover rig, reducing costs and eliminating more than 5 days of deferred production.

Integrated, rigless operation saves time and costs

SLB followed a systematic, integrated approach to plan the intervention with a coiled tubing unit instead of a conventional workover rig. The complete rigless solution included a coiled tubing unit, an ESP stinger, and an ESP retrieval tool.

Coiled tubing was rigged up to the well to pull the old ESP string through the tubing without a workover rig. The new ESP was subsequently run into the well using the same tool. When the ESP reached the Shuttle system’s docking station, the motor connector automatically orientated and connected, providing the electrical source to enable powering up.

The operation was completed in 47 hours with no operational or HSE issues and only 12 people involved rather than the 40 typically required to replace an ESP with a workover rig. In addition to saving approximately USD 95,000 by eliminating a rig, the customer avoided at least 5 days of deferred production.

Products Used