Monitor and analyze processes and downhole conditions in real time.
In a multiwell campaign, Abu Dhabi Company for Onshore Petroleum Operations Ltd. (ADCO) was facing Invisible Lost Time (ILT) challenges related to poor hole cleaning and potential stuck pipe risk. When preparing to drill a pilot well—a highly deviated oil producer—the operator planned a design with four sections: 16-in vertical, 12 1/4-in deviated, 8 1/2-in landing, and 6-in horizontal. The 12 1/4-in section presented the most challenges in terms of hole cleaning and stuck pipe risk given its profile—a build-and-hold 52° sail angle—and the planned use of a motor BHA. With these considerations, ADCO's main objectives were to drill each section shoe to shoe, maximize on-bottom ROP, and reduce connection time.
ADCO and SLB decided to implement a new workflow through the OptiWell service to detect and reduce ILT while maximizing on-bottom ROP. The SENSU system positions high-frequency digital sensors throughout the rig, providing full awareness of rig data and activity. A cuttings flowmeter, part of the CLEAR service, is used to acquire advanced cutting recovery measurements while drilling. Lastly, closing the loop of the wellbore surveillance operation, experienced performance analysts are deployed as part of the OptiWell service to further optimize drilling and eliminate flat time.
By using the OptiWell service, ADCO was able to complete the well in 36 days—2 days ahead of AFE—with no NPT and zero stuck pipe incidents. Specifically, in the challenging 12 1/4-in section, early detection and action taken upon signs of wellbore instability effectively prevented a stuck pipe incident in that section.
Throughout the operation, cuttings recovery and hole cleaning were both improved by changing drilling parameters. ADCO was able to reduce total connection time 35% (23 to 15 min/stand) in the 8 1/2-in section and 31% (22.5 to 15.5 min/stand) in the 6-in section. The operator also increased on-bottom ROP 18% (53 ft/h to 63 ft/h) in the 8 1/2-in section and 13% (63 ft/h to 71 ft/h) in the 6-in section.
These combined improvements in stuck pipe prevention, connection time, and hole cleaning circulation yielded an estimated cost savings of USD 564,600 for ADCO.
The pilot well was completed 2 days ahead of AFE, and further time-saving opportunities around the cleanup cycle process were identified.