Monitor and analyze processes and downhole conditions in real time.
Published: 02/24/2017
Published: 02/24/2017
Deepwater Gulf of Mexico hosts some of the most technically complex operations in the industry. Because a deepwater well can cost more than USD 150 million, even small improvements in efficiency can amount to millions in cost savings.
While developing an oil field in the Gulf of Mexico, an operator aimed to optimize common rig activity, enhance drilling operations, and continuously improve benchmark performance while ensuring adherence to strict HSE guidelines. The operator sought to achieve consistent improvement across three wells with step-by-step implementations addressing
Schlumberger collaborated with the operator to customize a plan using the OptiWell service. As a team, the companies worked to provide monitoring of surface and downhole data, event detection and reporting, KPI tracking, and fit-for-purpose workflows to meet the specific challenges faced throughout the entire well construction process.
A Schlumberger team was stationed at the operator's office to facilitate more regular interaction with the operator. After a prewell project meeting, Schlumberger, the operator, and the drilling contractor participated in knowledge-sharing workshops and formulated a plan to meet objectives. The plan included
KPIs for each hole section were tracked and compared with the benchmarks daily to identify opportunities for cost savings and performance improvements.
Additional Schlumberger drilling and measurement technologies were deployed to further enhance operational efficiency and save rig time.
The successful implementation of the OptiWell service—along with extensive collaboration between Schlumberger, the operator, the drilling contractor, and other third parties—resulted in best-in-class well performance by a number of parameters.
The operator set a record for the most footage drilled in the Gulf of Mexico in 24 hours—2,826 ft [861.4 m] drilled in the 16½-in × 19-in section. Over the course of three wells, average on-bottom ROP increased 93% from 73 ft/h to 141 ft/h, and average connection time was decreased from 28.5 min to 17 min. Additionally, BOP test times were reduced from 11.4 h to 3.6 h per test. As a result of the improved efficiency enabled by the OptiWell service on the deepwater Gulf of Mexico operation, the operator saved 36 drilling days and USD 13.3 million.
The integrated drilling solution enabled achieving best-in-class performance and completing drilling operations 45 days ahead of AFE.
Challenge: Optimize common rig activity and improve overall drilling performance without compromising HSE during well construction in deepwater Gulf of Mexico.
Solution: Customize a drilling strategy that included the OptiWell well construction performance service to monitor surface and downhole data to ensure that KPIs are met.
Results: Saved 36 drilling days and USD 13.3 million through best-in-class well performance that included