Reduce offshore drilling waste stream by up to 90%, reduce trips to shore, lower emissions and fuel use.
Published: 02/15/2016
Published: 02/15/2016
An operator in the Oso field in Ecuador sought a suitable location to handle large volumes of slurry for reinjection. However, an increase in the waste generated from drilling activities would also increase environmental and social risks. The objective for the operator was to identify and validate a centralized CRI facility area that would not negatively affect the community or environment.
M-I SWACO suggested implementing a FEED study to evaluate the subsurface and environmental feasibility of CRI and to identify the optimal operational and injection parameters for an environmentally safer, efficient, and cost-effective CRI. M-I SWACO first modeled the fracture propagation behavior using a fully planar 3D hydraulic fracturing simulator. Applying these techniques to the validation of subsurface conditions made it possible to identify containment and confinement formations and verify that the fracture domain was an acceptable distance from nearby wells and geological hazards.
The FEED study also included the selection of surface equipment for the project. Evaluating surface equipment considers the waste volume and streams involved in the process, including utilities and footprint. A centralized facility requires additional considerations for logistics and sufficient onsite temporary storage under high-volume scenarios. The surface equipment needs and sufficient space for temporary onsite storage were identified and included in a proposal for the necessary size of the facility.
Once the FEED study was completed, and prior to initiating operations, a complete set of injectivity tests was performed to deliver the first direct evaluation of injection pressure needed to conduct CRI operations. The test provided a reference line for the in situ parameters of the disposal formation, the means to calibrate the geomechanical model, and alignment of the hydraulic fracture simulations results.
Previously, a third-party vendor performed an injection test in the same area without considering all subsurface parameters, including the poroelasticity effect and the multiple fracturing complexities in the injection formation. The vendor's results indicated poor feasibility of CRI injection because of high pressures and the inability to inject more than 2.5 bbl/min [0.40 m3/min].
FEED engineers at M-I SWACO proposed a new procedure that considered the presence of the high poroelasticity conditions in the formation as a result of the technical subsurface evaluation. The new procedure included a correction in injection fluid properties to mitigate the effect of the poroelasticity while performing the injection test.
M-I SWACO performed the formation injection tests and deployed pressure analysis techniques to calculate the subsurface parameters for calibrating the geomechanical model previously constructed for the field and to verify the pressure conditions expected during operations. The assessments helped identify vertical fracture growth and reduced poroelasticity in the formation, allowing injection of up to 7.5 bbl/min [1.19 m3/min].
The new injection test results validated injectivity in the formation and demonstrated the importance of an adequate procedure and integrated subsurface assurance approach before the injection of the first slurry batch. Tests were completed without reaching the maximum allowable surface pressure—even at 7.5 bbl/min.
Challenge: Identify, evaluate, and design cuttings reinjection (CRI) technology for a centralized facility in an area with limited space and restricted permitting process for landfill disposal.
Solution: Execute a front-end engineering design (FEED) study to examine the basis of the design, surface and subsurface technical conditions, and implications to identify an environmentally feasible location for a centralized CRI facility.
Results: