Managed Pressure Drilling and Real-Time Produced Gas Measurement Using CARBONTRACKER Gas Meter, Thailand | SLB

Managed Pressure Drilling and Real-Time Produced Gas Measurement Using CARBONTRACKER Gas Meter, Thailand

Published: 06/10/2011

Blue hero texture
Well Information
 
Location Northeast Thailand
Well type Vertical (Gas)
Hole size 12¼-in & 8½-in
Open Interval Length 15,026 ft (4,580 m) MD

The situation

M-I SWACO provided Managed Pressure Drilling (MPD) services for a land based drilling project for an independent operator in Thailand. This was the first M-I SWACO MPD project in Thailand and the project presented unique challenges, including

  • remote drilling location
  • short delivery time frame
  • the ability to safely handle significant volumes of gas at surface.

M-I SWACO designed a fit-for–purpose package that allowed the operator to quickly respond to uncertain downhole pressure environments using proven AUTOCHOKE technology to safely control and vent any produced gas while controlling bottom hole pressure and without interrupting the drilling process.

The solution

An MPD equipment suite with the added ability to flow gas while drilling was determined as the best solution for this project.

The MPD equipment, in particular the AUTOCHOKE technology allowed the client to adjust the effective Mud Weight while drilling in response to the ever-changing downhole pressure environment. This was the most cost effective method to reduce non-productive time (NPT) throughout the drilling of the well. 

The results

It can be seen from the Drilling Curve and Reservoir Characterization graphs. The success of this operation, with regards to ROP, reduction in NPT and identifying the reservoir “sweet spots” (Reservoir Characterization).

Thailand: Managed Pressure Drilling (MPD) and real-time produced gas measurement using CARBONTRACKER gas meter
Drilling curve.
Thailand: Managed Pressure Drilling (MPD) and real-time produced gas measurement using CARBONTRACKER gas meter
Reservoir characterization.

"I am convinced that the MPD equipment provided a significant operational advantage that allowed this well, deepest in Thailand, to be drilled with fewer casing strings and minimal hole problems compared with similar wells drilled in Northeast Thailand.” —Julian Butcher, Vice-President, TATEX Thailand LLC

Location
Thailand, Asia, Onshore
Details

Challenge:

  • Challenging drilling in highly fractured carbonate reservoir with potential for high gas flow rates.
  • Wildcat well and operators limited experience in Thailand.
  • Historically slow drilling rates from other wells in the same area.

Solution:

  • MPD was considered as the technology for this project.
  • As this was the first M-I SWACO MPD project in Thailand, there were challenges associated with this well.
  • Remote location (Northeast Thailand).
  • Short equipment delivery time frame.
  • Equipment ability to safely handle significant volumes of gas at surface.
  • Operators ability to quickly respond to the uncertain downhole pressure environment.

Results:

  • Operators ability to quickly respond to the uncertain downhole pressure environment purpose” MPD package with ability to safely flow  and gas at surface, while drilling.
  • AUTOCHOKE, designed to maintain constant near bottom-hole pressure (Pressure Balance Choke).
  • CARBONTRACKER, designed to measure reservoir gasses at very low flow rates (Reservoir Characterization).
Products Used
Subscribe