BP Saves 12 Days of Downtime and 6,000-m3 Diesel Managing Deepwater Pipeline with the OLGA Simulator | SLB

BP Saves 12 Days of Downtime and 6,000-m3 Diesel Managing Deepwater Pipeline with the OLGA Simulator

Published: 06/06/2016

Blue hero texture

Flowline shutdowns cause significant subsea production losses

A BP deepwater oil field offshore Angola consists of two independent subsea production systems (SS1 and SS2). Multiphase production is gathered in subsea manifolds and routed to a single floating production, storage, and offloading (FPSO) vessel via insulated subsea flowlines and risers. A flow assurance management system, custom built within the OLGA simulator to represent the architecture of the production systems, provides a continuous window for observation of the multiphase flow behavior.

Because of the water depths and nature of the production fluids, the single biggest threat to flow assurance in the field is the potential for hydrate blockage during long production shutdowns. This is particularly critical for the large-bore lines in the production systems owing to the significant production losses associated with shutdowns. With no mature technology in the industry for the remediation of hydrate blockage in deepwater flowlines, hydrate management in the field focuses on prevention. In cold production restarts, therefore, flowlines are typically preconditioned by hot oil circulation (also known as hot dieseling) prior to restarting the wells.

Flow assurance simulations identify alternative restart procedure

Following an unplanned production shutdown of SS1, a 6-day production deferment occurred because the onboard diesel volume was below the requirement for hot oil circulation. Acquiring sufficient diesel for conventional preconditioning would have taken over a week, during which time the production deferment would have continued. 

What-if simulations were conducted using the online real-time flow assurance management system powered by the OLGA simulator. The flow assurance simulation identified an alternative to conventional preconditioning: The what-if simulation identified that the hot oil circulation operation could be modified for a more rapid restart with less diesel usage by having an initial batch of diesel “chased” by a batch of dead oil. Running the scenarios in what-if mode required less than 1 day for a flow simulation that would have required several days to execute with an offline simulation analysis. Such time savings are particularly important in critical scenarios that pose a high risk of additional deferred production. 

Because the concept was untested, there were concerns that swapping between the diesel and dead oil batches would cause delays. The output from the what-if scenarios showed that the operation was feasible, even with the delay caused by switching between the batches. A maximum target delay was identified in the flow assurance simulator and used along with other key tool parameters to draft a temporary alternative operating procedure. 

Alternative procedure becomes the reliable, more economical standard

Use of the temporary alternative operating procedure with reduced diesel requirements resulted in a successful restart. Because of the savings in diesel, the guidelines for this operation have been adopted as the standard operating procedure for the field. Two successful restarts took place in the first year of adopting the procedure to avoid deferrals equivalent to 12 days of downtime and save diesel volumes amounting to 6,000 m3.

BP Saves 12 Days of Downtime and 6,000-m3 Diesel Managing Deepwater Pipeline with the OLGA Simulator
Pressure and temperature trends from the field are compared with OLGA simulator scenarios using the new standard operating procedure. Although transient predictions may not give absolute values within close approximation to instruments in some instances, they give general trends with sufficient accuracy to help inform correct decision-making in critical scenarios.

Ongoing managed services from Schlumberger ensure the flow assurance management system's long-term effectiveness and provide monitoring and mitigation of flow assurance issues for the field. This solution reduces production deferrals and maintains pipeline integrity by identifying and overcoming issues that include potential hydrate blockage, possible scale deposition, and stringent limits on riser top velocities.

The proactive approach of the managed services ensures high system reliability, while technical support services provide guidance on how to best leverage the flow assurance management system. Additionally, the managed services provide remote assistance during field operations and enable collaboration among experts in Schlumberger and BP Angola to increase field knowledge and use the simulation tools effectively.

“We avoided significant production deferrals and reduced opex in the first year of using this flow assurance management system. The savings made in the field meant our investment in the pipeline management solution was soon recovered.”

Javier Canon, BP Angola Operations

Location
Angola, Africa, Offshore
Details

Challenge: Avoid the risk of significant deferred production after a production shutdown at an offshore Angola facility, when a timely restart was jeopardized by the lack of sufficient diesel for conventional preconditioning of the lines against hydrate formation.

Solution: Conduct a “what-if” scenario in the OLGA dynamic multiphase flow simulator to identify an alternative restarting method that uses less diesel.

Results: Successfully restarted with less diesel and prevented production deferment by following the alternative operating procedure, which was subsequently adopted as the field’s standard operating procedure. Avoided production deferment equivalent to 12 days of downtime while lowering diesel requirements by approximately 6,000 m3.

Products Used