Integrated Well Construction Achieves Record Performance in Middle Eastern Field | SLB

Integrated Well Construction Achieves Record Performance in Middle Eastern Field

Published: 03/17/2021

Concrete blue texture
Chart showing drilled well vs. offset performance.
By integrating well construction technologies, an operator drilled an entire well in 26.2 days, which was a 5.5% improvement over the previous field record. The 121/4-in section was the fastest drilled in the field, surpassing the previous record by 20%.
Location
Middle East, Asia, Onshore
Background

In a multiwell, multiyear lump-sum turnkey (LSTK) project where the drilling environment is a constant challenge, the LSTK business model aims to reduce well time and costs by integrating well engineering and fit-for-purpose technologies.