40% incremental oil from extended-reach multizone well | SLB

Manara system controls extended-reach multizonal well, enabling 40% incremental oil

minus
陆上

An operator wanted to optimize cleanup and production in all six zones of an extended-reach horizontal well passing through four reservoir segments with different permeabilities. Manara™ production and reservoir management system—which enables selective, real-time flow measurement and electric control of each zone—delivered a 40% oil increment by managing flow during cleanup to enable production from two damaged zones that would have been impossible to produce conventionally. It also optimized interval control valve (ICV) settings and reduced cleanup and production optimization time by at least 2 days.

Continuously optimize oil production without intervention

Extended-reach drilling (ERD) enables reservoir access with lower overall well construction costs and significant reduction of surface infrastructure costs and footprint. For example, drilling an extremely long horizontal well from a location on land reduces costs by eliminating the much higher costs of building offshore platforms and subsequent logistics.

Along with infrastructure complexities, extended-reach wells bring additional difficulties. In long, horizontal multizone wells that produce from multiple reservoirs with different properties, uneven drawdown can hinder production and promote early gas or water breakthrough. In addition, high friction in the long horizontal causes a heel-to-toe pressure loss effect that exacerbates reservoir pressure differences.

For a new extended-reach well, an operator needed a way to optimize production from six productive zones in four reservoirs with dissimilar permeabilities and pressures. Earlier in the project, the operator used conventional extended-reach completions composed of screens and passive inflow control devices (ICDs). Although the ICDs and nozzles were engineered for the expected reservoir conditions, uncertainty in estimated reservoir properties resulted in the wells experiencing early gas breakthrough. Because the wells did not have a monitoring system to enable better understanding of flow potential, the wells required multiple interventions to manage the production uncertainty.

For the new well, the operator wanted to address the uncertainties with active flow control and measurements to better characterize zone potential and to drain oil without gas breakthrough. This would only be possible with a completion that could be installed to the full depth of the long horizontal well and deliver zonal measurements and control from surface in real time.

Graph showing effects of cleanup and choke optimization on zonal production.
On initial cleanup (1), zones 3 and 4 contributed no oil production. To clean up those zones (2), the engineers choked back zones 5 and 6. After the damaged zones started to flow (3), all valves were opened fully to determine initial production. Finally (4), optimizing the valve settings maximized recovery, resulting in 25% higher production compared with production when opening all valves fully.

Manage drilling damage and reservoir uncertainties in real time

At the initial well kickoff, engineers fully opened the ICVs for all six zones and measured oil production, with significant contributions from zones 5 and 6, less from zones 1 and 2, and no flow from zones 3 and 4. Reservoir analysis indicated that zones 3 and 4 should be significant producers, so the operator believed the permeability was damaged with drilling mud. With a conventional completion, cleaning the tight zones would have been impossible.

With the Manara system in the well, the engineering team choked zones 5 and 6 to increase drawdown in the damaged zones. The pressure change induced flow that cleaned up the permeability damage without further intervention. After the zones stabilized, the engineers reopened all the ICVs and measured overall production, with contributions from all zones, including the two previously damaged zones.

To maximize well production, the engineers then used SLB production optimization digital workflows for intelligent completions to calculate the optimal setting for the ICV in each zone. The result was a production increase of 25% compared with the production when all valves were fully open—including 40% from the two damaged zones that would not have produced at all without the real-time drawdown control.

Using the electric completion system for the cleanup and optimization process saved the operator approximately 2 days compared with using slower hydraulically actuated valves.

相关产品