Cimarex Saves 6 Days of Rig Time in Permian Basin | SLB

Cimarex Energy Co. saves six days of rig time in Permian Basin

minus
Permian Basin, Texas, 美国, North America, 陆上

Kick off from pilot hole cement plug and drill curve and lateral in reservoir known to induce high levels of shock and vibration.

Establish new procedures to reduce drilling time

Cimarex Energy Co. wanted to reduce drilling time while kicking off a pilot hole and drilling a curve and lateral in West Texas. Historically, Cimarex has used three separate assemblies in three runs to kick off from the plug, complete the curve and drill to TD. The operator required a specially designed BHA to meet the demands of drilling in an area of the Permian basin known to induce shock and vibration.

Use high build rate RSS to drill to TD in one run

  • Drilled to TD with PowerDrive Archer™ high build rate rotary steerable system.
  • Optimized bit selection with IDEAS™ integrated design platform from SLB.
  • Modeled optimal drilling fluid with VIRTUAL HYDRAULICS™ drilling fluid simulation software
  • POLY-PLUS RD™ high-molecular-weight liquid clay inhibitor to water-base mud to provide cuttings encapsulation and shale stabilization.
  • Use shale shaker for exceptional solids removal.
  • Saved six days of rig time.
  • Set Cimarex records for fastest curve (1,544 ft/d) and lateral (1,956 ft/d) sections drilled.
  • Eliminated a dedicated kick-off assembly and time drilling.

The PowerDrive Archer high build rate rotary steerable system was selected to perform the sidetrack and drill the well to TD faster and eliminate time associated with multiple trips and slide drilling. This system is a true hybrid of push- and point-the-bit technology that delivers high-dogleg severities up to 18°/100 ft. It also enables the system to perform fast, reliable openhole sidetracks in any direction.

SLB supplied directional drilling services to optimized the SHARC high-abrasion-resistance PDC drill bit using IDEAS integrated design platform. Using 4D, time-based simulations, the IDEAS platform models the cutting interface in real time, eliminating costly trial-and-error field tests. To reduce shock and vibration, SLB determined optimum fluid characteristics using VIRTUAL HYDRAULICS software.

Graph: Cimarex Energy Saves 6 Days of Rig Time Using Integrated Schlumberger Services in Permian Basin
The PowerDrive Archer RSS system set new records by drilling the curve at 1,544 ft/d and the lateral at 1,956 ft/d in one run, which when compared with previous records of 1,332 ft/d and 1,647 ft/d, saved the operator 6 days of rig time.

Saved six days by drilling record curve and lateral in single run

Using an engineered BHA design including PowerDrive Archer high build rate rotary steerable system and SHARC PDC drill bit, Cimarex drilled the well with one BHA, resulting in a time savings of six days. The separation off of the cement plug was gained at 80 ft/h, eliminating time-drilling intervals while rotating. The curve and lateral sections were completed in one run and Cimarex set two company records for drilling speed—the curve at 1,544 ft/d and the lateral at1,956 ft/d.

While drilling, the operation encountered higher-than-expected shock and vibration. Predictive modeling from i-DRILL engineered drilling system design eliminated the drillstring as the cause. VIRTUAL HYDRAULICS software was then used and determined the fluid had caused the heavy shock and vibration. SLB experts worked closely to evaluate and model the appropriate fluid. Once the shock and vibration were reduced, the PowerDrive Archer high build rate rotary steerable system performed to specifications. Cimarex plans to use this time-saving system when drilling future wells in the Permian basin.

"We successfully kicked off the pilot hole cement plug with a high-dogleg-capable rotary steerable system from SLB, and we drilled a record curve and a record lateral in the same run."

Spencer Bryant, Drilling Engineer, Cimarex Energy Co.