Overcome production challenges in the field or at the production facility using fit-for-purpose solutions.
Production ExPRESS™ rapid production response solutions quickly enabled production with a customized solution that kept the waxy oil at a constant 60 degC until it was ready for transport.
A major energy company in India encountered heavy paraffin-laden oil at a remote location more than 100 km from the nearest processing facility. The operator needed a way to create early cash flow while measuring the well’s potential production to determine whether building processing and export facilities was economically feasible. A common way to do this is to install an early production facility (EPF).
The Production ExPRESS solutions package helped meet the operator's early cash flow objectives and deliver the required data for further decision making. The project was successfully completed after achieving an outstanding record of zero HSE incidents and zero NPT.