Significantly improve footage and ROP in hard-to-drill formations.
已发表: 02/29/2016
已发表: 02/29/2016
As part of a campaign to develop the Iracema Norte field in the Santos basin offshore Brazil, Petrobras was drilling a well with a J-shaped profile in the hard heterogeneous carbonates characteristic of this presalt basin. The reservoir interval targeted by this well, located in the Lula field, is composed of organic microbial carbonates and other sediments such as silicate nodules and layers of low porosity.
In the reservoir intervals of offset wells, Petrobras encountered ring-out dull characteristics on the shoulder of the bit, low penetration rates, and stick/slip vibration, which often resulted in unplanned bit trips. Petrobras wanted to avoid these performance issues and reach TD of the 12 1/4-in interval in one run at an average ROP greater than 2 m/h for its ultradeepwater well.
As part of a joint presalt optimization project, Schlumberger and Petrobras selected a customized StingBlade conical diamond element bit for the presalt cluster of the Santos basin that would improve bit durability and mitigate stick/slip. Using the IDEAS integrated drillbit design platform, Schlumberger designed a bit that combined Stinger conical diamond elements and PDC cutting elements and features:
To enhance drilling performance, optimal drilling parameters would be defined and simulated in the i-DRILL engineered drilling system design, and drilling performance would be monitored continuously in real time.
Using the StingBlade bit, Petrobras achieved an average ROP of 2.9 m/h—45% higher than the goal set by Petrobras—and reached interval TD in 95.5 hours—11 hours ahead of schedule. Petrobras drilled the 274-m interval in one run with only minor damage observed to the StingBlade bit (graded at 2-3-WT-A-X-1-CT-TD). Compared with the 12 1/4-in intervals of offset wells, this hole interval was drilled 25% farther and at 11.5% greater ROP.
The StingBlade bit also produced cuttings that were significantly larger than in offset wells, making it easier for mud loggers to identify the characteristics of the formation drilled. Schlumberger monitored downhole conditions in real time, and drilling parameters were adjusted throughout the entire run to mitigate stick/slip. Petrobras intends to apply the successful performance improvement measures from this well interval to future operations in the Santos basin.
Challenge: Reach interval TD of complex presalt well in a single run with an average ROP greater than 2 m/h.
Solution: Use an application-specific StingBlade conical diamond element bit from Smith Bits for increased cutting structure durability and improved ROP.
Results: