Underream while drilling in a single run.
已发表: 01/27/2014
已发表: 01/27/2014
During development of a shallow oil field in the Persian Gulf, the operator needed to drill and underream a 14 1/2-in section through interbedded layers of limestone, anhydrates, and shale. A conventional steerable BHA was used to drill the 14 1/2-in section of an offset well to TD. Then a second run was performed to open the hole to 16 in. The two runs took almost 17 days to complete.
To optimize the drilling process for the second well, the operator decided to drill and underream simultaneously. The plan was to directionally drill 1,200 ft while building inclination from approximately 5° to 25° at TD and underreaming in the same run.
The i-DRILL integrated dynamic system analysis service was used to model a custom BHA system and recommend drilling parameters to optimize the drilling process and mitigate shock and vibration. The BHA included a PowerDrive Xceed 900 rotary steerable system (RSS), an MDi816 PDC drill bit from Smith Bits, a Schlumberger company, a Rhino XS hydraulically expandable reamer, and WELL COMMANDER ball activated drilling valve from M-I SWACO, a Schlumberger company.
After considering several different i-DRILL scenarios, the optimum drilling parameters were identified to preserve the bit and reamer cutting structure while keeping the surface torque below a 20,000-lbf.ft torque limit. Strict adherence to the recommended parameters was key to obtaining the desired directional drilling results, while mitigating the risk of shock-related failure.
The BHA with an RSS and underreamer, which included a dedicated cleanout BHA for the rathole, drilled and underreamed the interval in less than 11 days for a total savings of 6.2 days and USD 744,000. Postrun analysis showed minimal damage to the cutting structure even after drilling through the hard Aruma shale.
The BHA with an RSS and underreamer, which included a dedicated cleanout BHA for the rathole, drilled and underreamed the interval in less than 11 days for a total savings of 6.2 days and USD 744,000. Postrun analysis showed minimal damage to the cutting structure even after drilling through the hard Aruma shale.
Challenge: Directionally drill and underream a 14 1/2-in interval through interbedded layers of limestone, anhydrates, and shale in a shallow offshore formation while mitigating shock and vibration
Solution: Design a BHA system and recommend optimal drilling parameters using the i-DRILL integrated dynamic system analysis service
Results: Simultaneously drilled and underreamed the section in approximately 11 days, saving more than 6 days of rig time and approximately USD 744,000