Perform inflow testing, negative testing, and displacement in a single trip.
已发表: 01/01/2010
已发表: 01/01/2010
Well Information |
|
Location | Saudi Arabia |
Dates | October 2008 to December 2009 |
Tool types | 7-in Heavy-Duty RAZOR BACK*, 7-in MAGNOSTAR*, 9⅝-in WELL COMMISSIONER |
Application | Inflow testing 7-in liner lap on drill-out and clean-up trip |
Mud types | Some OBM, mostly WBM (polymer) |
Mud weights | 70-148 pcf (936-1978 lb/gal) |
Well Depths | 10,400-16,500 ft (3,170-5,029 m) |
WELL COMMISSIONER setting depths | 6,200-15,200 ft (1890-4633 m) |
Hole Angles at WELL COMMISSIONER setting depth | 0-76˚ |
Inflow test differential pressure range | 1,000-4,100 psi |
Underbalancing fluid | Water (some diesel) |
Drill Pipe sizes | 5-in., 3½-in., 4-in |
Maximum bottom hole temperatures | 1165˚-340˚ F (74˚-171˚C) |
Maximum lengths of cement drilled inside 7-in. liners | 1300-600 ft (91-183 m) Max 2,700 ft (823 m) |
Rotating Speeds drilling cement | 30-80 RPM |
Number of wells | 94 |
After setting and cementing the 7-in. liner, the operator’s standard procedure would be to make two trips into the well. The first would be to drill the shoe track and the hard cement left behind after the liner was cemented. The second trip typically would be for running a retrievable packer to perform an inflow test on the 7-in liner lap.
The operator selected the M-I SWACO WELL COMMISSIONER tool, Heavy-Duty RAZOR BACK* CCT and MAGNOSWEEP* or MAGNOSTAR string magnet tools as a one-trip system was designed to clean the liner to total depth. The WELL COMMISSIONER liner testing tool is especially engineered to allow inflow and negative tests to be carried out on a liner overlap and the liner shoe track simultaneous with the wellbore clean-up trip. For this application, the technology would be used to drill out the remaining cement on the top cement plug, in order to avoid a “muddy” shoe, in addition to drilling the shoe track. Furthermore, it also was designed so the 7-in liner lap could be inflow tested.
Certain modifications in equipment and procedures evolved during the course of this campaign to allow routine drilling of significant quantities of cement, along with the shoe track, as planned on the inflow test and clean-up run.
Before initiating the job and to save both time and money, M-I SWACO Specialized Tools personnel collaborated closely with the client to optimize their liner inflow testing process. A special sleeve was designed to actively protect the WELL COMMISSIONER tool while drilling cement and liner accessories, including those comprising PDC-drillable aluminium and cast iron. The drilling fluid also had to be re-engineered to ensure no solid settling would occur during the four-to-five- hour inflow test. This viscous pill was devised to complement the drilling fluid system. Prior to conducting the inflow test, this pill was pumped ahead of the underbalanced fluid.
The WELL COMMISSIONER was landed on the liner top with the bit on bottom. The required liner inflow test was completed to specification. After drilling the shoe track and with the bit hard on bottom during the 4-5 hour inflow testing of the liners, it became practice to spot a viscous pill 200 feet (61 m) above the bit, around the bit and 200 feet (61 m) inside the drillpipe to stabilize the static mud while monitoring the inflow test. During the course of the project, a number of equipment and procedural modifications were implemented.
With this new solution, the 7-in. liner cement/shoe tracks typically have been drilled just prior to a four-to-five-hour inflow test and cleaned out successfully; all on a single trip. This saved, on average, more than 30 hours of rig time per job, compared to the previous procedure using two separate runs. At the end of 2009, a total of 94 consecutive jobs had been completed with no recordable non productive time (NPT).
WELL COMMISSIONER tool emerging from Inflow Test and clean-up in Saudi Arabia, after the cement and shoe track had been drilled on the same trip.
WELL COMMISSIONER tool emerging from Inflow Test and clean-up in Saudi Arabia, after the cement and shoe track had been drilled on the same trip hundred feet of cement in a single clean-up trip. The one-trip clean-up reduced rig time considerably.”
Todd Adams, M-I SWACO Manager Specialized Tool
If you’d like to know more about the WELL COMMISSIONER tool and how it’s performing for our other customers, please call the M-I SWACO office nearest you.
Challenge: After setting and cementing the 7-in. liner, the operator’s standard procedure would be to make two trips into the well.
Solution: The operator selected the M-I SWACO WELL COMMISSIONER tool, Heavy-Duty RAZOR BACK CCT and MAGNOSWEEP or MAGNOSTAR string magnet tools as a one-trip system was designed to clean the liner to total depth.
Results: With this new solution, the 7-in. liner cement/shoe tracks typically have been drilled just prior to a four-to-five-hour inflow test and cleaned out successfully; all on a single trip. This saved, on average, more than 30 hours of rig time per job, compared to the previous procedure using two separate runs.