Cement Plug with CemNET Technology Enables Sidetrack After Lost Circulation Event, Pakistan | SLB

Cement Plug with CemNET Technology Enables Sidetrack After Lost Circulation Event, Pakistan

已发表: 05/01/2018

Concrete blue texture
To deliver lightweight cement with high compressive strength and avoid losses, Schlumberger designed and delivered a 2.4-m3 [15-bbl] cement plug comprising LiteCRETE slurry at 1.44 g/cm3 [12 lbm/galUS] and CemNET technology at 4.3 kg/m3 [1.5 lbm/bbl]. No losses were seen after the plug hit the perforations, and the well had full returns during reverse circulation. After setting, the plug was tagged with 5-t weight on bit and the well pressure tested to 6.9 MPa [1,000 psi].
To deliver lightweight cement with high compressive strength and avoid losses, Schlumberger designed and delivered a 2.4-m3 [15-bbl] cement plug comprising LiteCRETE slurry at 1.44 g/cm3 [12 lbm/galUS] and CemNET technology at 4.3 kg/m3 [1.5 lbm/bbl]. No losses were seen after the plug hit the perforations, and the well had full returns during reverse circulation. After setting, the plug was tagged with 5-t weight on bit and the well pressure tested to 6.9 MPa [1,000 psi].
地点
Pakistan, 亚洲
Feature.PageContent.LeftRailDetails.Title

Pakistan
Southern Provinces

Lithology
Naturally fractured limestone

Depleted zone depth, m [ft]
1,400 [4,600]

Initial mud weight, g/cm3 [lbm/galUS]
1.08 [9.0]

Loss-control mud weight, g/cm3 [lbm/galUS]
1.03 [8.6]

Sidetrack kickof point, m [ft]
1,050 [3,400]

背景
An operator was preparing to abandon a depleted zone and then sidetrack the well at a shallower depth to access additional reserves. Immediately after the depleted zone’s packer was milled, the well incurred circulation losses of 3.2–4.8 m3/h [20–30 bbl/h] across the perforations. The mud was loaded with sawdust and rice husk, reducing density to maintain the fluid level in the well for cementing.
相关产品
Subscribe